Bechtel Corporation. East Bay Municipal Utility District Part VII Project : Drawings for Camanche Dam Mokelumne River Project.January 1962
License Application of Oakdale and South San Joaquin Irrigation DistrictsCalifornia. July 30, 1948
Application for License by Oakdale and South San Joaquin Irrigation Districtsfor Tulloch Project. 1950
Application for Amendment of License of Oakdale and South San Joaquin Irrigation DistrictsProject 2005. May 3, 1950
Notebook 1948
Notebook 1949
Notebook 1950
Notebook 1960
Report 1948
Bonner, F.E. OSSID Diversion Dams.September 6, 1949
Bonner, F.E. Report to Oakdale and South San Joaquin Irrigation Districts on OSSID Project.September 23, 1949
Hartley, H.E. Report Covering General Conditions and Storage Needs of the Oakdale Irrigation District.February 20, 1950
Stivers, T.P. Report on the South San Joaquin Irrigation District.February 1950
Bonner, F.E. Memorandum on Output of Stanislaus Project.September 1, 1950
Bonner, F.E. Report to Oakdale and South San Joaquin Irrigation Districts on Donnell's Project Output.October 22, 1951
Research notes 1950
Tables 1948-1950
Tables undated
Worksheets 1921-1951
Oakdale Irrigation Districtand South San Joaquin Irrigation District. Tri-Dam Project : Drawings for Schedule No. III Donnells Power Plant and Appurtenances.January 30, 1953
Oakdale Irrigation Districtand South San Joaquin Irrigation District. Tri-Dam Project : Drawings for Schedule No. IV Beardsley Dam, Power Plant, Afterbay Dam, and Appurtenances.January 30, 1953
Marliave, Chester. Preliminary Geological Report on Beardsley Dam Site Located Across Middle Fork Stanislaus River in Tuolumne County, California for Oakdale and South San Joaquin Irrigation Districts.May 4, 1949
Addendum 1959
Application by Oroville-Wyandotte Irrigation Districtfor License from Federal Power Commission. 1951
Application by Oroville-Wyandotte Irrigation Districtfor License from Federal Power Commission. 1951
Application research data 1951
Before the Federal Power Commission F.P.C. License No. 2088 of Oroville-Wyandotte Irrigation District Application for Amendment of Plans.March 9, 1960
Bid forms 1959
Contracts 1959-1960
Contracts 1960
Cost estimates 1950-1960
Hearings 1950-1953
Hearings 1955
Hearings 1955
Hearings 1957-1961
Miscellaneous data 1950
News clippings 1950-1959
News clippings 1960
News clippings 1960-1963
Operation Studies 1957-1958
Photographs undated
Photographs undated
Plans 1958
Agreement between Oroville-Wyandotte Irrigation District and Yuba County Water District. March 22, 1958
Report 1950
Bonner, F. E. Oroville-Wyandotte Irrigation District South Fork Project.November 21, 1950
Harper, Harry A. Oroville-Wyandotte Irrigation District South Fork of Feather River Project Cost Estimate of Tunnel Alternate on M.R. Ditch.May 5, 1952
Bonner, F.E. OWID Forbestown Afterbay.January 31, 1953
Norris, S. J. Preliminary Report on Proposed Development of Water Resources of the South Fork of Feather River and Contiguous Areas for Power and Irrigation.March 1, 1954
Norris, S.J. Memorandum on Review by Division of Water Resources of Plan Development for South Fork Feather River.September 30, 1954
Bonner, F.E. Comment on DWR Report of 12/15/54 South Fork of Feather River Development.December 30, 1954
Reports 1955-1956
Bonner, F.E. Report for Oroville-Wyandotte Irrigation District on Proposed Water and Power Development of South Fork of Feather River California.June 10, 1958
Bonner, F.E. Report for Oroville-Wyandotte Irrigation District on Proposed Water and Power Development of South Fork of Feather River California.June 10, 1958
Bonner, F.E. Report for Oroville-Wyandotte Irrigation District on Proposed Water and Power Development of South Fork of Feather River California.June 10, 1958
Bonner, F.E. OWID South Fork Project.June 10, 1958
State of California Department of Water Resources. Report on Proposed Oroville-Wyandotte Irrigation District Water and Power Development on South Fork of Feather River.September 1958
State of California Department of Water Resources. Report on Proposed Oroville-Wyandotte Irrigation District Water and Power Development on South Fork of Feather River.September 1958
Report 1958
Report 1958
Bechtel Corporation. Engineering Feasibility Report on the South Fork Project.April 5, 1960
Research notes 1959
Revenue Bonds 1960
Tables 1950-1960
Working papers undated
Bechtel Corporation. Oroville-Wyandotte Irrigation District Oroville, California South Fork Project : Drawings for All Schedules. March 16, 1959
Bechtel Corporation. Oroville-Wyandotte Irrigation District Oroville, California South Fork Project : Drawings for All Schedules.March 16, 1959
Bechtel Corporation. Oroville-Wyandotte Irrigation District Oroville, California : Drawings for Construction of the South Fork Project.March 1960
Lost Creek Reservoir 1958
Bonner, F.E. Oroville-Wyandotte Irrigation District MR Canal.August 19, 1953
Harper, H.A. Report of Investigation of Miners Ranch Damsite.October 10, 1952
Harper, H.A. South Fork Feather River Project Investigation of Rock Quarry Sly Creek Damsite.April 28, 1952
Series 4. Richvale Irrigation District 1886-1967
Applications to appropriate unappropriated water 1953
Applications 1953-1962
Applications 1962
Briefs 1961
Correspondence 1950-1958
Correspondence 1959-1960
Correspondence 1961
Correspondence 1962-1963
Cost estimates 1951-1960
Cost estimates 1961-1962
Exhibits 1961
Exhibits 1963
Hearings 1950
Hearings 1954-1961
Hearings January - June 1962
Hearings July - December 1962
Hearings 1963
Maps 1886-1955
Maps 1956-1962
News clippings 1952, 1959
News clippings 1961-1963
Petitions 1953-1954
Press Releases 1953
Westinghouse Electric Corporation. Westinghouse Vertical Water Wheel Synchronous Generators.February 1950
State of California Department of Water Resources Division of Resources Planning. Investigation of Upper Feather River Basin Development.February 1957
Weber, Charles M. A Modified Plan for Development of the Water and Power Resources of the Feather River Basin.January 20, 1958
Carroll E. Bradberry and Associates. Reservoir Effects on Temperature Middle Fork Feather River, Clio to Nelson Point Reservoir.1961
Carroll E. Bradberry and Associates. Streamflow Accretions Middle Fork Feather River Clio to Bidwell Bar.1961
Reports 1949-1963
Harper, Harry A. Report of Reconnaissance Geology.March 23, 1953
Report 1953-1959
Bonner, F.E. Proposed Development of Middle Feather River California by Richvale Irrigation District.March 21, 1956
McHuron, Clark E. Report of Preliminary Reconnaissance Geologic Field Trip for the Development of the Middle Fork of the Feather River, California.February 1958
State of California Dept. of Water Resources. Impairment of Middle Feather Runoff.July 24, 1961
Vaughan, Tim M. A Preliminary Report on the Fishery and Recreational Potential of the Middle Fork of the Feather River with Proposed Richvale Irrigation District Development.September 10, 1961
Reports 1961
Bonner, F.E. Middle Feather Project of Richvale and Associated Districts Report on Channel Releases.August 8, 1962
Miscellaneous reports 1962
Miscellaneous reports 1962-1963
Statements before the State of California State Water Rights Board 1950-1959
Statements before the State of California State Water Rights Board 1960-1961
Tables 1959-1960
Tables 1961
Tables 1962-1963
Worksheets 1951
Worksheets 1958-1961
Durrell, Cordell. Report to the Board of Directors of the Richvale Irrigation District on the Geologic Conditions Surrounding the Proposed Damsite at Clio, California.January 1953
California State Department of Water Resources.Division of Resources Planning. Geologic Report on Grizzly Valley Dam Site on Big Grizzly Creek.1957
Series 5. Sacramento Municipal Utility District 1926-1961
Applications 1948-1957
Correspondence 1954
Correspondence 1955-1957
Cost estimates 1954-1955
Exhibits 1956
Exhibits 1956
Exhibits 1956
Maps undated
News clippings 1947-1958
Photographs 1961
Plates 1949-1957
Donald R. Warren Co. Ventura County Flood Control District Zone One Flood Control and Water Conservation.1945
Office of the City Engineer, City of Sacramento. A Water Supply for Sacramento from the American River Discussion of a Possible Contract with the United States Bureau of Reclamation.April 1957
Cost Estimates American River Hydro,1952
Bonner, F.E. American River Development Sacramento-SMUD Cooperation.October 20, 1954
Sacramento Municipal Utility District. Upper American River Project.undated
Review notes 1958
Tables 1954
Tables 1955-1957
Worksheets 1927-1935
Worksheets 1954-1955
Worksheets 1956
Bonner, F.E. Report to Federal Power Commission in Mokelumne River Situation.April 20, 1926
Fowler, Frederick Hall. Appraisal of Plant and Equipment Gilmore Oil Company, Ltd. and Affiliated Companies.October 1, 1929
Exhibit 1957
Hearings 1958
News clippings 1954-1962
Trinity River calculations and diagrams undated